Water wells are an extremely important resource for any landowner, but there are some abandoned wells that exist that can pose a hazard to people, animals, and groundwater. An abandoned water well is a well that has been taken out of use, a well that is in such a state of disrepair that using it for any purpose is impractical, or a well that is a physical hazard or threatens to contaminate aquifers.

According to Kansas law K.A.R. 28-30-7, all abandoned water wells are required to be plugged. A landowner is allowed to do this themselves, or they may hire a Kansas licensed water well contractor to do so. There are both hand-dug wells and cased wells that may need to be abandoned, and they have slightly different methods for plugging. 

The general steps for plugging are:

Step 1: Prepare site by removing all pumping equipment and any debris.

Step 2: Remove the top of the casing and cut off 3 feet below the surface.

Step 3: Disinfect water by adding chlorine, see Table 1 of the K-State Extension publication for the amount needed: MF935 Plugging Abandoned Wells--Water Quality Series

Step 4: Fill the water zone with porous material, meaning sand or gravel less than 1 inch in size. Refer to the plugging diagrams for examples (Figures 1 & 2).
 

Plugging diagram for a hand-dug well, before and after plugging

Figure 1. Plugging diagram for a hand-dug well, before and after plugging.
 

Plugging diagram for a drilled well

Figure 2. Plugging diagram for a drilled well, before and after plugging.

Step 5: Add compacted clay above the water zone. Stop when you are five feet below the ground level.

Step 6: Add a grout plug. This can be bentonite clay, cement grout, or neat cement. See the K-State Extension publication for grout recipes, and to estimate how much is needed for your specific well size. MF935 Plugging Abandoned Wells--Water Quality Series. The thickness of the grout plug should be about 6 inches for most wells.

Step 7: Fill in the rest of the hole to the surface using compacted subsoil, and then use topsoil for the very surface. This will settle over time, so mounding the soil up about 10” should be about right.

Step 8: Fill out a plugging record form WWC-5P and submit to the Kansas Department of Health and Environment’s Bureau of Water-Geology Section. This form is available at: https://www.kdheks.gov/waterwell/

 

Source : ksu.edu

Trending Video

Experience Fendt at EIMA 2026 | Official Aftermovie

Video: Experience Fendt at EIMA 2026 | Official Aftermovie



Five days, thousands of visitors, countless conversations and unforgettable moments.

Join us as we look back on an exciting week at EIMA International 2026 in Bologna, where farmers, contractors, customers, partners and fans from across Europe came together to experience the latest Fendt innovations.

From the European premiere of the Fendt 1100 Vario MT to the celebration of the 50,000th Fendt 900 Vario with a limited edition, as well as harvesting highlights including the Fendt IDEAL 9T, Fendt Rotana, Fendt Slicer and Fendt Katana 850, our booth showcased efficient solutions. Thank you to everyone who visited our stand, shared their passion for agriculture and helped make EIMA 2026 such a memorable event.